Tabela de Custos - Versão 028.1 - ENC. SOCIAIS 84,44%

C3156 - CONCRETO PROJETADO (MEDIDO NA MÁQUINA 35MPa)
Preço Adotado: 1.450,4200 Unid: M3
Código Descrição Unidade Coeficiente Preço Total
EQUIPAMENTOS (CHORARIO)
I0628 GRUPO GERADOR 36 KVA (CHI) H 1,0000 27,5494 27,5494
I0742 GRUPO GERADOR 36 KVA (CHP) H 2,0000 65,3268 130,6537
I0566 BETONEIRA COM MOTOR A DIESEL (CHI) H 0,0000 22,8100 0,0000
I0680 BETONEIRA COM MOTOR A DIESEL (CHP) H 1,0000 29,0963 29,0963
I0569 BOMBA COM MOTOR A DIESEL (CHI) H 0,3000 25,5177 7,6553
I0683 BOMBA COM MOTOR A DIESEL (CHP) H 0,7000 34,2543 23,9780
I0614 COMPRESSOR DE AR 250 PCM (CHI) H 0,0000 45,0499 0,0000
I0728 COMPRESSOR DE AR 250 PCM (CHP) H 1,0000 135,2089 135,2089
I0636 MÁQUINA P/CONCRETO PROJETADO (CHI) H 2,0000 40,8594 81,7187
I0750 MÁQUINA P/CONCRETO PROJETADO (CHP) H 0,7000 60,1079 42,0756
I0598 CARRINHO DE MÃO (CHI) H 0,0000 0,3594 0,0000
I0712 CARRINHO DE MÃO (CHP) H 6,0000 0,5289 3,1732
TOTAL EQUIPAMENTOS (CHORARIO)481,1090
MAO DE OBRA
I2391 PEDREIRO H 4,0000 24,1600 96,6400
I2543 SERVENTE H 20,0000 18,4600 369,2000
TOTAL MAO DE OBRA465,8400
SERVIÇOS
C3130 AREIA DE RIO - EXTRAÇÃO M3 0,7830 8,7961 6,8873
C3253 BRITA PRODUZIDA PARA USOS DIVERSOS M3 0,9830 100,7005 98,9886
TOTAL SERVIÇOS105,8759
MATERIAIS
I0805 CIMENTO PORTLAND KG 560,0000 0,7100 397,6000
TOTAL MATERIAIS397,6000
Total Simples 1.450,42
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 1.450,42