〈〈 VOLTAR ⎙ IMPRIMIR ⬇ DOWNLOADS

Tabela de Custos - Versão 028.1 - ENC. SOCIAIS 84,44%

C1948 - PONTO HIDRÁULICO, MATERIAL E EXECUÇÃO
Preço Adotado: 256,4700 Unid: PT
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2543 SERVENTE H 2,5000 18,4600 46,1500
I2320 ENCANADOR H 3,0000 23,4800 70,4400
I0043 AJUDANTE DE ENCANADOR H 3,0000 19,1000 57,3000
TOTAL MAO DE OBRA173,8900
MATERIAIS
I2201 TUBO PVC SOLDÁVEL DE 32MM (1') M 5,0000 8,5600 42,8000
I1293 JOELHO PVC ROSCAVEL DE 1" UN 1,0000 5,9400 5,9400
I2200 TUBO PVC SOLDÁVEL DE 25MM (3/4') M 1,2000 4,3300 5,1960
I1426 LUVA REDUÇÃO PVC SOLDAVEL DE 32X25MM UN 1,0000 3,3900 3,3900
I1973 TE PVC SOLDAVEL 32MM UN 1,0000 4,1200 4,1200
I0884 COTOVELO PVC SOLDAVEL DE 25MM UN 2,0000 0,7900 1,5800
I1412 LUVA PVC SOLDAVEL DE 32MM UN 2,0000 2,1800 4,3600
I0805 CIMENTO PORTLAND KG 2,5000 0,7100 1,7750
I0441 CAL HIDRATADA KG 2,5000 0,9600 2,4000
I0885 COTOVELO PVC SOLDAVEL DE 32MM UN 4,0000 2,6500 10,6000
I0108 AREIA GROSSA M3 0,0035 119,5800 0,4185
TOTAL MATERIAIS82,5795
Total Simples 256,47
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 256,47