| C0442 - BOMBA CENTRÍFUGA DE 1/3 CV, INCLUSIVE MAT.DE SUCÇÃO |
| Preço Adotado: 782,5800 |
Unid: UN |
|
| Código
| Descrição |
Unidade
| Coeficiente |
Preço |
Total |
| MATERIAIS |
| I2286 |
VÁLVULA RETENÇÃO. PÉ C/CRIVO - 20MM (3/4') |
UN |
1,0000 |
59,5400 |
59,5400 |
| I2223 |
TUBO PVC RÍGIDO ROSCÁVEL DE 3/4" |
M |
6,0000 |
11,1100 |
66,6600 |
| I0252 |
BOMBA CENTRIFUGA P=1/3CV |
UN |
1,0000 |
504,9600 |
504,9600 |
| I0026 |
ADESIVO PARA TUBO DE PVC RIGIDO |
KG |
0,2500 |
63,3600 |
15,8400 |
| I1180 |
FITA DE VEDAÇÃO |
M |
3,0000 |
0,3600 |
1,0800 |
| I1298 |
JOELHO PVC ROSCAVEL DE 3/4" |
UN |
1,0000 |
2,8700 |
2,8700 |
| TOTAL MATERIAIS | 650,9500 |
| MAO DE OBRA |
| I2320 |
ENCANADOR |
H |
2,5000 |
26,1800 |
65,4500 |
| I0043 |
AJUDANTE DE ENCANADOR |
H |
2,5000 |
21,1000 |
52,7500 |
| I2312 |
ELETRICISTA |
H |
0,5000 |
26,8500 |
13,4250 |
| TOTAL MAO DE OBRA | 131,6250 |
|
| Total Simples |
782,58 |
| Encargos |
INCLUSOS |
| BDI |
0,00 |
| TOTAL GERAL |
782,58 |
|