| C0446 - BOMBA CENTRÍFUGA DE 3 CV, INCLUSIVE MAT.DE SUCÇÃO |
| Preço Adotado: 2.031,5600 |
Unid: UN |
|
| Código
| Descrição |
Unidade
| Coeficiente |
Preço |
Total |
| MAO DE OBRA |
| I2320 |
ENCANADOR |
H |
3,0000 |
26,1800 |
78,5400 |
| I0043 |
AJUDANTE DE ENCANADOR |
H |
3,0000 |
21,1000 |
63,3000 |
| I2312 |
ELETRICISTA |
H |
0,8000 |
26,8500 |
21,4800 |
| TOTAL MAO DE OBRA | 163,3200 |
| MATERIAIS |
| I2288 |
VÁLVULA RETENÇÃO. PÉ C/CRIVO - 40MM (1 1/2') |
UN |
1,0000 |
111,5400 |
111,5400 |
| I2216 |
TUBO PVC RÍGIDO ROSCÁVEL DE 1 1/2" |
M |
6,0000 |
34,2500 |
205,5000 |
| I0026 |
ADESIVO PARA TUBO DE PVC RIGIDO |
KG |
0,3000 |
63,3600 |
19,0080 |
| I1180 |
FITA DE VEDAÇÃO |
M |
3,0000 |
0,3600 |
1,0800 |
| I1291 |
JOELHO PVC ROSCAVEL DE 1 1/2" |
UN |
1,0000 |
14,8200 |
14,8200 |
| I0255 |
BOMBA CENTRIFUGA P=3CV |
UN |
1,0000 |
1.516,2900 |
1.516,2900 |
| TOTAL MATERIAIS | 1.868,2380 |
|
| Total Simples |
2.031,56 |
| Encargos |
INCLUSOS |
| BDI |
0,00 |
| TOTAL GERAL |
2.031,56 |
|