Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C1902 - PIA DE AÇO INOX (2.00X0.58)m C/ 2 CUBAS E ACESSÓRIOS
Preço Adotado: 1.648,4300 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2543 SERVENTE H 2,5000 20,2600 50,6500
I2391 PEDREIRO H 2,5000 26,8600 67,1500
I2320 ENCANADOR H 4,0000 26,1800 104,7200
I0043 AJUDANTE DE ENCANADOR H 4,0000 21,1000 84,4000
TOTAL MAO DE OBRA306,9200
MATERIAIS
I1180 FITA DE VEDAÇÃO M 2,2600 0,3600 0,8136
I0169 AÇO CA-60 KG 1,1400 7,5900 8,6526
I1605 PEDRISCO M3 0,0400 100,5000 4,0200
I1648 PIA EM INOX C/ 2 CUBAS 2.00x0.58 UN 1,0000 597,3100 597,3100
I2131 TORNEIRA DE PRESSÃO CROMADA LONGA P/PIA 3/4' UN 2,0000 110,3800 220,7600
I1863 SIFÃO CROMADO 2" UN 2,0000 209,3700 418,7400
I0805 CIMENTO PORTLAND KG 16,3800 0,7100 11,6298
I0108 AREIA GROSSA M3 0,0300 119,5800 3,5874
I2265 VÁLVULA AMERICANA P/ PIA 1 1/2"X 3/4" UN 2,0000 38,0000 76,0000
TOTAL MATERIAIS1.341,5134
Total Simples 1.648,43
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 1.648,43