〈〈 VOLTAR ⎙ IMPRIMIR ⬇ DOWNLOADS

Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C2000 - POSTE C/ACESSÓRIOS ATÉ A ENTRADA DA SUBESTAÇÃO ABRIGADA
Preço Adotado: 11.926,9900 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MATERIAIS
I1549 OLHAL PARA PARAFUSO DE 5/8'' UN 3,0000 12,4100 37,2300
I2162 TUBO CERÂMICO DE 300MM M 3,0000 72,4300 217,2900
I1272 ISOLADOR PORCELANA TIPO DISCO 175MM DE VIDRO UN 9,0000 96,5400 868,8600
I0914 CRUZETA EM CONCRETO ARMADO-PADRÃO COELCE UN 4,0000 80,0100 320,0400
I8373 CABO ISOLADO 15KV 35MM2 M 40,0000 52,6000 2.104,0000
I0549 CHAVE FUSIVEL INDICADORA 15KV/50A-RUPTURA 1200A UN 3,0000 357,2800 1.071,8400
I1719 POSTE DE CONCRETO DUPLO T (11MX400KG), RESISTÊNCIA NOMINAL 400KG, H=11,00M, PESO APROXIMADO 1158KG UN 1,0000 1.294,3000 1.294,3000
I2163 TUBO AÇO GALVANIZADO DE 100MM (4') M 6,0000 167,5700 1.005,4200
I1564 PARA-RAIOS TIPO VALVULA - 15KV UN 3,0000 192,5100 577,5300
I1535 MUFLA INTERNA/EXTERNA 15KV UN 8,0000 272,0200 2.176,1600
I1568 PARAFUSO ABAULADO M16X150MM UN 6,0000 7,6800 46,0800
I1217 GANCHO OLHAL UN 3,0000 11,6700 35,0100
TOTAL MATERIAIS9.753,7600
MAO DE OBRA
I1088 ELETROTECNICO MONTADOR H 27,0000 32,5400 878,5800
I0042 AJUDANTE DE ELETRICISTA H 27,0000 21,1000 569,7000
I2312 ELETRICISTA H 27,0000 26,8500 724,9500
TOTAL MAO DE OBRA2.173,2300
Total Simples 11.926,99
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 11.926,99