Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C2090 - QUADRO P/ MEDIÇÃO EM POSTE DE CONCRETO
Preço Adotado: 1.758,5600 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MATERIAIS
I0841 CONECTOR PARA HASTE TERRA UN 1,0000 2,8300 2,8300
I0551 CHAVE GERAL 3X200A-BASE DE MARMORE UN 1,0000 444,0700 444,0700
I0355 CABO ISOLADO PVC 750V 10MM2 M 1,0000 9,3300 9,3300
I1243 HASTE DE ATERRAMENTO COPPERWELD 3/4'' x 3M UN 1,0000 131,8700 131,8700
I0436 CAIXA TIPO 'J' 50X60X27CM UN 1,0000 89,8800 89,8800
I0338 CABO COBRE NU 25MM2 M 2,0000 23,7100 47,4200
I1071 ELETRODUTO DE PVC RIGIDO 1/2'' M 1,5000 3,6700 5,5050
I0285 BUCHA DE FERRO GALVANIZADO 1 1/2'' UN 3,0000 1,3500 4,0500
I0126 ARRUELA DE FERRO GALVANIZADO 1 1/2'' UN 3,0000 1,1500 3,4500
I1720 POSTE DE CONCRETO DUPLO T ( 8MX300KG), RESISTÊNCIA NOMIAL 300KG, H= 8,00M, PESO APROXIMADO 708KG UN 1,0000 790,0000 790,0000
TOTAL MATERIAIS1.528,4050
MAO DE OBRA
I0042 AJUDANTE DE ELETRICISTA H 4,8000 21,1000 101,2800
I2312 ELETRICISTA H 4,8000 26,8500 128,8800
TOTAL MAO DE OBRA230,1600
Total Simples 1.758,56
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 1.758,56