Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C3017 - PIA DE AÇO INOX (1.20x0.60)m C/ 1 CUBA E ACESSÓRIOS
Preço Adotado: 748,1900 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2543 SERVENTE H 2,0000 20,2600 40,5200
I2391 PEDREIRO H 2,0000 26,8600 53,7200
I2320 ENCANADOR H 2,0000 26,1800 52,3600
I0043 AJUDANTE DE ENCANADOR H 2,0000 21,1000 42,2000
TOTAL MAO DE OBRA188,8000
MATERIAIS
I2503 TORNEIRA DE METAL BRANCO 3/4", CANO LONGO (PADRÃO POPULAR) UN 1,0000 47,4900 47,4900
I2487 PIA EM INOX C/ 1 CUBA 1,20x0,60 - C18/A304 UN 1,0000 219,9000 219,9000
I0169 AÇO CA-60 KG 0,6000 7,5900 4,5540
I1605 PEDRISCO M3 0,0260 100,5000 2,6130
I1863 SIFÃO CROMADO 2" UN 1,0000 209,3700 209,3700
I2344 FITA VEDA ROSCA 25M x 3/4" UN 1,1000 9,1000 10,0100
I0805 CIMENTO PORTLAND KG 9,8300 0,7100 6,9793
I2264 VÁLVULA AMERICANA P/PIA 3 1/2" UN 1,0000 56,2000 56,2000
I0108 AREIA GROSSA M3 0,0190 119,5800 2,2720
TOTAL MATERIAIS559,3883
Total Simples 748,19
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 748,19