〈〈 VOLTAR ⎙ IMPRIMIR ⬇ DOWNLOADS

Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C3019 - PIA DE AÇO INOX (3.00x0.60)m C/ 1 CUBA E ACESSÓRIOS
Preço Adotado: 1.956,6100 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2543 SERVENTE H 2,7500 20,2600 55,7150
I2391 PEDREIRO H 2,7500 26,8600 73,8650
I2320 ENCANADOR H 3,5000 26,1800 91,6300
I0043 AJUDANTE DE ENCANADOR H 3,5000 21,1000 73,8500
TOTAL MAO DE OBRA295,0600
MATERIAIS
I2503 TORNEIRA DE METAL BRANCO 3/4", CANO LONGO (PADRÃO POPULAR) UN 1,0000 47,4900 47,4900
I2491 PIA EM INOX 3,00x0,60 C/ 1 CUBA - C18/A304 UN 1,0000 1.355,3500 1.355,3500
I0169 AÇO CA-60 KG 1,5000 7,5900 11,3850
I1605 PEDRISCO M3 0,0610 100,5000 6,1305
I1863 SIFÃO CROMADO 2" UN 1,0000 209,3700 209,3700
I2344 FITA VEDA ROSCA 25M x 3/4" UN 1,1300 9,1000 10,2830
I0805 CIMENTO PORTLAND KG 22,9300 0,7100 16,2803
I2264 VÁLVULA AMERICANA P/PIA 3 1/2" UN 0,0000 56,2000 0,0000
I0108 AREIA GROSSA M3 0,0440 119,5800 5,2615
TOTAL MATERIAIS1.661,5503
Total Simples 1.956,61
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 1.956,61