Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C3148 - CONCRETAGEM DE BASES TUBULÃO AR COMPRIMIDO ATE 12m
Preço Adotado: 2.089,2700 Unid: M3
Código Descrição Unidade Coeficiente Preço Total
EQUIPAMENTOS (CHORARIO)
I0658 TALHA MANUAL (CHI) H 0,0000 0,1895 0,0000
I0771 TALHA MANUAL (CHP) H 1,0000 0,2666 0,2666
I0628 GRUPO GERADOR 36 KVA (CHI) H 0,0000 29,9694 0,0000
I0742 GRUPO GERADOR 36 KVA (CHP) H 1,0000 67,7468 67,7468
I0569 BOMBA COM MOTOR A DIESEL (CHI) H 0,4000 27,3177 10,9271
I0683 BOMBA COM MOTOR A DIESEL (CHP) H 0,6000 36,0543 21,6326
I0614 COMPRESSOR DE AR 250 PCM (CHI) H 0,0000 47,4699 0,0000
I0728 COMPRESSOR DE AR 250 PCM (CHP) H 1,0000 137,6289 137,6289
I0593 CAMPÂNULA DE AR COMPRIMIDO (CHI) H 0,0000 13,7470 0,0000
I0707 CAMPÂNULA DE AR COMPRIMIDO (CHP) H 1,0000 18,7641 18,7641
I0651 RESERVATÓRIO DE AR COMPRIMIDO (CHI) H 0,0000 3,3943 0,0000
I0764 RESERVATÓRIO DE AR COMPRIMIDO (CHP) H 1,0000 4,6330 4,6330
TOTAL EQUIPAMENTOS (CHORARIO)261,5991
MAO DE OBRA
I2136 TRABALHADOR AR COMPRIMIDO H 4,0000 26,8600 107,4400
I2578 SINALEIRO H 1,0000 26,8600 26,8600
I2391 PEDREIRO H 1,0000 26,8600 26,8600
I2543 SERVENTE H 4,0000 20,2600 81,0400
TOTAL MAO DE OBRA242,2000
SERVIÇOS
C3270 CONCRETO P/VIBR., FCK=15MPa COM AGREGADO PRODUZIDO (S/ TRANSP.) M3 1,0000 456,2383 456,2383
C0216 ARMADURA CA-50A MÉDIA D= 6,3 A 10,0mm KG 90,0000 12,3324 1.109,9160
TOTAL SERVIÇOS1.566,1543
MATERIAIS
I2579 TORRE METALICA UN 0,0070 2.760,2100 19,3215
TOTAL MATERIAIS19,3215
Total Simples 2.089,27
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 2.089,27