C3153 - CONCRETAGEM DE TUBULÃO (CAMISA/ENCHIM.) AR COMP. D=1,60m ATÉ 12m |
Preço Adotado: 4.270,1400 |
Unid: M |
|
Código
| Descrição |
Unidade
| Coeficiente |
Preço |
Total |
EQUIPAMENTOS (CHORARIO) |
I0658 |
TALHA MANUAL (CHI) |
H |
0,0000 |
0,1895 |
0,0000 |
I0771 |
TALHA MANUAL (CHP) |
H |
1,0000 |
0,2666 |
0,2666 |
I0628 |
GRUPO GERADOR 36 KVA (CHI) |
H |
0,0000 |
29,9694 |
0,0000 |
I0742 |
GRUPO GERADOR 36 KVA (CHP) |
H |
1,0000 |
67,7468 |
67,7468 |
I0569 |
BOMBA COM MOTOR A DIESEL (CHI) |
H |
0,4000 |
27,3177 |
10,9271 |
I0683 |
BOMBA COM MOTOR A DIESEL (CHP) |
H |
0,6000 |
36,0543 |
21,6326 |
I0614 |
COMPRESSOR DE AR 250 PCM (CHI) |
H |
0,0000 |
47,4699 |
0,0000 |
I0728 |
COMPRESSOR DE AR 250 PCM (CHP) |
H |
1,0000 |
137,6289 |
137,6289 |
I0593 |
CAMPÂNULA DE AR COMPRIMIDO (CHI) |
H |
0,0000 |
13,7470 |
0,0000 |
I0707 |
CAMPÂNULA DE AR COMPRIMIDO (CHP) |
H |
1,0000 |
18,7641 |
18,7641 |
I0651 |
RESERVATÓRIO DE AR COMPRIMIDO (CHI) |
H |
0,0000 |
3,3943 |
0,0000 |
I0764 |
RESERVATÓRIO DE AR COMPRIMIDO (CHP) |
H |
1,0000 |
4,6330 |
4,6330 |
TOTAL EQUIPAMENTOS (CHORARIO) | 261,5991 |
MAO DE OBRA |
I2136 |
TRABALHADOR AR COMPRIMIDO |
H |
7,1000 |
26,8600 |
190,7060 |
I2578 |
SINALEIRO |
H |
3,6000 |
26,8600 |
96,6960 |
I2391 |
PEDREIRO |
H |
3,6000 |
26,8600 |
96,6960 |
I2543 |
SERVENTE |
H |
7,1000 |
20,2600 |
143,8460 |
TOTAL MAO DE OBRA | 527,9440 |
SERVIÇOS |
C1405 |
FORMA PLANA CHAPA COMPENSADA RESINADA, ESP.= 12mm UTIL. 3 X |
M2 |
8,8000 |
146,4680 |
1.288,9184 |
C3270 |
CONCRETO P/VIBR., FCK=15MPa COM AGREGADO PRODUZIDO (S/ TRANSP.) |
M3 |
2,0100 |
456,2383 |
917,0389 |
C0216 |
ARMADURA CA-50A MÉDIA D= 6,3 A 10,0mm |
KG |
100,0000 |
12,3324 |
1.233,2400 |
TOTAL SERVIÇOS | 3.439,1973 |
MATERIAIS |
I2579 |
TORRE METALICA |
UN |
0,0150 |
2.760,2100 |
41,4032 |
TOTAL MATERIAIS | 41,4032 |
|
Total Simples |
4.270,14 |
Encargos |
INCLUSOS |
BDI |
0,00 |
TOTAL GERAL |
4.270,14 |
|