〈〈 VOLTAR ⎙ IMPRIMIR ⬇ DOWNLOADS

Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C3607 - CONFECÇÃO E MONTAGEM DE PÓRTICO INDICATIVO PRÉ-MOLDADO DE CONCRETO P/TERMINAL RODOVIÁRIO
Preço Adotado: 15.888,5600 Unid: UN
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2543 SERVENTE H 71,8000 20,2600 1.454,6680
I2391 PEDREIRO H 36,9000 26,8600 991,1340
I1858 SERRALHEIRO H 101,0000 26,8600 2.712,8600
I1879 SOLDADOR H 8,6000 27,7000 238,2200
I2395 PINTOR H 24,0000 26,8600 644,6400
TOTAL MAO DE OBRA6.041,5220
MATERIAIS
I0534 CHAPA DE AÇO FINA 3/16" (4,75MM - 38,00KG/M2) KG 145,9000 7,7400 1.129,2660
I0102 ARAME GALVANIZADO N.18 BWG KG 8,7400 23,5700 206,0018
I0799 CIMENTO BRANCO KG 22,0000 4,1800 91,9600
I2099 TINTA PRIMARIA L 5,4000 7,8300 42,2820
I0280 BRITA M3 3,4200 100,5000 343,7100
I1872 SOLDA 50X50 KG 6,2000 147,1300 912,2060
I0471 CANTONEIRA METÁLICA DE 4" X 4" X 3/8" (14,60KG/M) KG 57,7000 9,2300 532,5710
I0805 CIMENTO PORTLAND KG 1.632,0000 0,7100 1.158,7200
I0163 AÇO CA-50 KG 461,9000 7,1000 3.279,4900
I0108 AREIA GROSSA M3 3,5700 119,5800 426,9006
I2097 TINTA LATEX ACRÍLICA L 10,8000 22,2000 239,7600
TOTAL MATERIAIS8.362,8674
EQUIPAMENTOS (CHORARIO)
I0584 CAMINHÃO COMERC. EQUIP. C/GUINDASTE (CHI) H 6,0000 64,9912 389,9470
I0705 CAMINHÃO COMERC. EQUIP. C/GUINDASTE (CHP) H 6,0000 172,7113 1.036,2676
I0682 BETONEIRA ELÉTRICA 580L (CHP) H 2,1000 27,5970 57,9536
TOTAL EQUIPAMENTOS (CHORARIO)1.484,1682
Total Simples 15.888,56
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 15.888,56