Tabela de Custos - Versão 028 - ENC. SOCIAIS 114,15%

C4630 - REINSTALAÇÃO DE PONTO HIDRÁULICO, MATERIAL E EXECUÇÃO
Preço Adotado: 133,0700 Unid: PT
Código Descrição Unidade Coeficiente Preço Total
MAO DE OBRA
I2320 ENCANADOR H 1,5000 26,1800 39,2700
I2543 SERVENTE H 1,2500 20,2600 25,3250
I0043 AJUDANTE DE ENCANADOR H 1,5000 21,1000 31,6500
TOTAL MAO DE OBRA96,2450
MATERIAIS
I2201 TUBO PVC SOLDÁVEL DE 32MM (1') M 1,2000 8,5600 10,2720
I2200 TUBO PVC SOLDÁVEL DE 25MM (3/4') M 1,2000 4,3300 5,1960
I1293 JOELHO PVC ROSCAVEL DE 1" UN 1,0000 5,9400 5,9400
I1426 LUVA REDUÇÃO PVC SOLDAVEL DE 32X25MM UN 1,0000 3,3900 3,3900
I0884 COTOVELO PVC SOLDAVEL DE 25MM UN 1,0000 0,7900 0,7900
I1973 TE PVC SOLDAVEL 32MM UN 1,0000 4,1200 4,1200
I1412 LUVA PVC SOLDAVEL DE 32MM UN 1,0000 2,1800 2,1800
I0805 CIMENTO PORTLAND KG 1,2500 0,7100 0,8875
I0441 CAL HIDRATADA KG 1,2500 0,9600 1,2000
I0885 COTOVELO PVC SOLDAVEL DE 32MM UN 1,0000 2,6500 2,6500
I0108 AREIA GROSSA M3 0,0017 119,5800 0,2033
TOTAL MATERIAIS36,8288
Total Simples 133,07
Encargos INCLUSOS
BDI 0,00
TOTAL GERAL 133,07